Group files suit to stop Missouri Gulch housing

Action cites CEQA violations, parking and more
musicWave

A group of local residents have filed a lawsuit to stop the planned Missouri Gulch housing project in Mariposa.

Called the Jones and Bullion Safety Committee, the group filed the suit on Oct. 19 in Mariposa County Superior Court, saying the county acted illegally in approving the housing project.

A letter sent to the county says the group is composed of “neighborhood residents and community members dedicated to advocating for and preserving the safety of the established residential neighborhood along Jones and Bullion streets, particularly in the northeast section of Mariposa, north of the courthouse.”

No names were associated with the letter sent to the Mariposa County Board of Supervisors other than the lawyer it has retained, Babak Naficy of San Louis Obispo.

There are four parties named as defendants in the lawsuit: Mariposa County Board of Supervisors, YF Real Estate Holdings,

Community Housingworks and Mogavero Architects.

YF Read Estate Holdings is a subsidiary of the Yosemite Conservancy, the group that owns the land where the project will be located as well as a key piece of land across the street near the VFW where there was talk of adding additional parking.

The lawsuit comes after the board approved moving forward with the project during a lengthy meeting held in September.

The project calls for 80 units of housing in five, three-story buildings to be constructed on just over three acres at the intersection of Jones and Bullion street, across from the VFW and next to the PG&E building in Mariposa.

The key to the project was a grant application that was due on Sept. 30 which would be for $27.5 million, of which $19 million would go to Community Housing Works (CHW), the nonprofit housing group which would lead the construction of the complex. It was not clear when the state might make a decision on the grant though officials felt it might be in early 2027.

A big focus of the project was for workforce housing, something that has been lacking in Mariposa County for quite some time. Many local agencies, including the John C. Fremont Healthcare District and the National Park Service submitted written information asking to reserve part of the housing for their workers.

The lawsuit

The suit lists two causes of action as the grounds for bringing the matter to court.

The first cause of action is “violation of CEQA (California Environmental Quality Act), failure to adequately analyze project impacts and feasibility and efficacy of mitigation.”

The second cause of action is violation of CEQA , failure to prepare an environmental impact report (EIR).

In the first cause of action, the group claims the “county abused its discretion and violated CEQA by adopting and relying on an MND that does not comply with CEQA mandates.”

MND means mitigated negative declaration, which was part of the approval by the supervisors that was passed unanimously by the board.

Naficy, who was hired by the local group, said he specializes in “land use and environmental law” and has been involved in cases across California.

He was not sure how long the case might take, but speculated it could be “nine months a year and a half.”

Jennifer McGrath, Mariposa County Counsel, did respond via email but had no comments on most issues.

She wrote “no comment” in response to the following questions:

• At what point in time do you have to respond to the filing given it involves CEQA?

• Does the grant application continue forward and will the suit have any impact on the state’s consideration?

• Has this issue been discussed with the board of supervisors and has any action taken place?

• Is there any consideration being given to modifying what was previously approved by the board as a result of the court filing?

Concerning hiring of outside counsel, she did send the contract which is with Colantuon Highsmith Whatlet, PC of Grass Valley and was on Nov. 17.

The firm wrote in its letter it charges between $245 and $650 an hour for the time law clerks and attorneys and between $170 and $220 an hour for paralegals and legal assistance.

“As a courtesy to you, however, we agree to cap our rate for this project at $450 an hour,” wrote Michael G. Colantuono, who indicated he would be the lead attorney on the case.

That rate is good through Dec. 1, 2027, it stated.

The parking

The plaintiffs focus heavily on the parking situation associated with Missouri Gulch — a topic that was discussed at length at the meeting in September.

The proposal at the meeting was for there to be 87 off-street parking spots but the requirement, according to the county based on state laws, is for 116.

That’s where the discussion turned to the piece of land across the state directly behind the VFW. That land, too, is owned by the Yosemite Conservancy. During the September meeting, officials said the conservancy had agreed to allow that land to be used for parking and it would mean an additional 29 spaces, thus meeting the requirements.

However, it was also stated by development officials during the meeting they were looking for other uses of that property, including possible retail spots and more.

“The project as approved will not provide adequate parking,” states the lawsuit.

Another issue that remains foggy is if the conservancy still owns the land or has transferred it to the development company.

“I am not entirely sure who owns what,” said Naficy, adding that’s why all of the parties were named in the action. He said the same is true for the land across the street which was discussed for the additional parking.

The suit cites county code which states a “multi-family residential project must provide a minimum of 1.5 parking spaces per unit for studio and one-bedroom apartments and two parking paces per unit for two or more bedroom apartments.”

Based on that, the suit claims, it would require 156 parking spaces.

What isn’t clear is how recent laws passed in California can exempt some projects from having to meet minimum local requirements and how those laws override local ordinances.

Naficy said he does not think those laws, including Title 24, are applicable in this case and it will be based on Mariposa County codes.

In the filing, the local group said, according to the county resolution, the applicant has “agreed to provide 116 parking spaces allowed by state (sic) without requesting additional concessions.”

It further stated the “final parking configuration remained unresolved at the time of project approval.”

Another point made in the court filing claims the county “did not undertake any adequate analysis of the environmental impacts associated with adding parking beyond the 87 spaces.”

It cites the lack of curb and gutter in the surrounding neighborhood which “would affect public safety,” including “displacing pedestrians, obstructing driveway sight lines and negatively affect emergency vehicle access.”

The lawsuit also cites many other issues, including drainage in the area, emergency access and evacuation, fire safety and more.

The action by the local group are requesting the following from the court:

• That the court issue an alternative and peremptory writ of mandate commanding respondents to set aside, invalidate and void the county’s approval of the Missouri Gulch project and adoption of the MND.

• For declaratory judgment, stating that respondents’ approval of the MND was in violation of CEQA.

• For a temporary restraining order, preliminary injunction and permanent injunction prohibiting any action in furtherance of the Missouri Gulch project until adequate environmental documents are certified to the satisfaction of the court.

• For an award of costs and attorney’s fees, and for such other further relief as the court deems just an proper.

Collateral damage?

Another aspect of the grant application was about other projects that would come along with larger award.

There has been $8.5 million earmarked for those projects.

One was a car rental program that would have eight cars available for rent to anyone in the community.

Another was upgrading of the trailhead expansion for the Stockton Creek Preserve. (See related story about the preserve.)

A third was upgrading the YARTS stops in Mariposa to include covers as well as digital boards indicating bus information.

The Southern Sierra Miwuk Nation is also targeted to get funding for its food program. The money would expand the current program offered by the tribe.

Mother Lode Job Training, too, has funds earmarked for expansion of workforce development. Those funds would include hiring two full-time people for the entire six years of the grant cycle.

It remains unclear if these programs, too, are impacted by the lawsuit.

Responses (0)

    Related posts

    featured
    Kellie FlanaganK
    Kellie Flanagan
    ·November 25, 2026

    Man dies, woman is injured following motorcycle crash

    featured
    Kellie FlanaganK
    Kellie Flanagan
    ·November 25, 2026

    EASTERN MADERA HAPPENINGS

    featured
    Kellie FlanaganK
    Kellie Flanagan
    ·November 25, 2026

    Winter wonderland slated at Chukchansi

    featured
    Kellie FlanaganK
    Kellie Flanagan
    ·November 25, 2026

    Breaking bad, er, board, was fun martial arts event

    More from author

    featured

    Young patients experience a unique ‘marathon’ event

    Kellie Flanagan·November 25, 2026
    featured

    Pupdate: Rescued dog family going to Silicon Valley

    Kellie Flanagan·November 25, 2026
    featured

    Surprise! Six puppies are rescued

    Kellie Flanagan·November 25, 2026
    featured

    Work on Highway 41 near Fresno is going well at the five-month mark

    Kellie Flanagan·November 25, 2026